SAP Horror Stories: Why Skipping the As Designed Stage is So Expensive

22nd July 2025

•

By Harrison Price

•

SAP Horror Stories: Why Skipping the As Designed Stage is So Expensive

SAP Horror Stories: 4 Homeowners Who Skipped the 'As Designed' Stage - and Paid the Price

When it comes to building regulation compliance, skipping the "As Designed" SAP stage might seem like a shortcut - but it often leads straight into expensive delays, rework, or even planning rejection. These four stories show how neglecting early-stage SAP advice led to real-world problems and unnecessary costs.

TL;DR? Listen to the article.

by Harpr Surveyors | Horror Stories when skipping the As Designed stage In SAP

👻 Story 1: The Overheating Ordeal

📍 Project:

Two semi-detached new builds in Cambridgeshire

⚠️ What Went Wrong:

The developer skipped design-stage SAP, assuming high-spec glazing would comply

🔍 Missed in SAP Design:

Large south-facing windows triggered a Part O overheating failure

🛠️ The Fix:

Retrofitted brise soleil and delayed handover by 5 weeks

💸 Cost Impact:

~£5,000 in materials, labour, and delays

✅ Lesson:

Design-stage SAP would’ve flagged overheating risks early and suggested simpler solutions

Full Story:
The project consisted of two semi-detached homes built with modern, minimalist architecture - clean lines, open-plan living, and large full-height windows. The developer felt confident in their glazing package and believed the high-spec triple glazing would be sufficient to pass Building Regulations. Unfortunately, they skipped the As Designed SAP stage, relying instead on a last-minute As Built assessment.

By the time the report was submitted, it flagged a significant overheating risk under Part O due to the expansive south-facing glazing and insufficient cross-ventilation. Without fixed shading or openable windows in key locations, the homes didn’t comply. The only solution was to retrofit horizontal brise soleil units - both expensive and visually intrusive - and resubmit the SAP documents, delaying final sign-off and move-in dates by over a month.

Story 1 The Overheating Ordeal - SAP Horror Stories

👻 Story 2: The Ventilation Void

📍 Project:

Bungalow split into two flats for private rental

⚠️ What Went Wrong:

The owner assumed extractor fans and background vents would be sufficient and skipped any design-stage SAP input.

🔍 Missed in SAP Design:

Ventilation rates didn't meet Part F compliance; cross-flow ventilation was inadequate and affected EPC results

🛠️ The Fix:

MVHR installation, including ducting and electrical work, plus internal redecoration.

💸 Cost Impact:

  • MVHR system + install: £3,800
  • Delays to EPC issue/rental start: ~£2,000 lost income
  • Total: ~£5,800

✅ Lesson:

SAP at the design stage ensures adequate ventilation design and coordination with other building services.

Full Story:
This client had recently converted a detached 1960s bungalow into two self-contained flats. The aim was to get both on the rental market quickly, but unfortunately, they didn’t consult a SAP assessor during the design stage. The M&E design included simple extract fans and background trickle vents, assuming this would satisfy ventilation requirements.

However, at As Built SAP stage, we found the proposed ventilation rates were far too low for the new internal layout - especially with open-plan kitchens and small bedrooms. The flats couldn’t demonstrate compliance with Part F. Worse, the openable window areas were insufficient for purge ventilation in key spaces. The only viable fix was installing MVHR (Mechanical Ventilation with Heat Recovery) units - requiring core drilling, new ducting runs, and redecoration. This delayed the EPC issue, and therefore the tenancy start, by nearly two months.

👻 Story 3: The Insulation Illusion

📍 Project:

Loft conversion in a mid-terrace 1930s property

⚠️ What Went Wrong:

The architect used assumed U-values and neglected to model thermal bridging, leading to unexpected SAP failures.

🔍 Missed in SAP Design:

Cold bridging at steel supports and dormer cheeks caused significant heat loss.

🛠️ The Fix:

Opened finished walls to add insulation and reran SAP with updated specifications.

💸 Cost Impact:

  • Additional insulation + redecoration: £2,200
  • Project delay: 3 weeks labour costs ~£1,200
  • SAP rerun + new EPC: £400
  • Total: ~£3,800

✅ Lesson:

Early SAP input gives clear, buildable targets and avoids last-minute remediation.

Full Story:
In this loft conversion project, the architect had used typical U-values and assumed the extension would easily pass compliance. Unfortunately, steel beam placements weren’t detailed with thermal breaks, and no thermal modelling was done. The dormer cheeks were left with a minimal insulation layer due to space constraints.

By the time the SAP was carried out at the As Built stage, the calculated heat loss through thermal bridging alone knocked the dwelling’s SAP score down by several points - pushing it below the Part L pass threshold. Since the internal finishes had already gone up, the builder had to open up the dormer cheeks and install insulated plasterboard with limited cavity space. That rework, plus a second SAP run, cost several weeks and over £3,000 in additional labour and materials.

👻 Story 4: The PV Payback Trap

📍 Project:

Eco-bungalow marketed as "zero carbon"

⚠️ What Went Wrong:

The SAP assessment was commissioned only after the roof had been built - resulting in underperforming PV due to poor orientation.

🔍 Missed in SAP Design:

Inadequate kWh/m² generation due to east-facing slope at 20° pitch - insufficient to meet TER.

🛠️ The Fix:

Extra PV panels installed on rear slope, plus inverter and consumer unit upgrade.

💸 Cost Impact:

  • Additional panels + inverter: £4,600
  • Electrical system alterations: £700
  • Total: ~£5,300

✅ Lesson:

SAP at design stage lets you optimise roof pitch and reduce reliance on costly add-ons.

Full Story:
An enthusiastic developer in Oxfordshire wanted to market their eco-bungalow as “zero carbon ready.” They assumed fitting 8 solar panels would easily help them hit SAP targets. But the SAP assessment was only commissioned after the structure was complete - meaning the east-facing roof with a shallow 20° pitch was already built.

The PV system couldn’t generate enough kWh annually to meet the DER/TER (Dwelling Emission Rate / Target Emission Rate) comparison, and there was no room left on the primary roof slope. The client ended up installing 4 additional panels on the rear slope and upgrading the inverter to handle the increased load - costing over £5,000 and requiring rework to the consumer unit.

Final Thoughts

Whether you're a homeowner, architect, or developer, involving SAP at the design stage isn't just about compliance - it's about saving time, reducing risk, and avoiding expensive surprises. Don't let your project become the next horror story.

Need help with SAP Design? Get in touch with Harpr Surveyors today.

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

Get Expert Help When You Need It

Choose surveying reliability and expertise with Harpr Surveyors!

Summarise the article with

Land Registry Plan Requirements

Land Registry Plan Requirements

Is your property plan ready for submission, or is it missing crucial details? Our latest guide breaks down the exact Land Registry plan requirements you need to follow to avoid frustrating rejections. Discover the common mistakes that lead to costly delays, see visual examples of what to do (and what not to do), and learn the basic rules for mapping everything from standard plots to complex maisonettes.

Site Footer & Information

About Harpr Surveyors

We provide accurate floor plans, scale plans, HM Land Registry compliant lease plans, EPCs, SAP calculations and retrofit assessments in accordance with PAS 2035 to estate agents, conveyancing solicitors and the public. We pride ourselves in the quality of our products.

Contact Details

Manobier, Fore Street, Nanpean, St. Austell, Cornwall, PL26 7YE

01726 254 220

Measured Surveys